APRIL REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and has moved into its fourth month. During this reporting period most of the activities were related to site work and building steel fabrication and installation. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (APRIL. 2018)
    • Site Grading for driveway and parking lot
    • Driveway concrete pour and curing
    • Parking lot concrete pour and curing
    • Building Steel fabrication
    • Start of Building Frame Installation

 

  • UPCOMING WORK (MAY. 2018)
    • Complete Building frame installation
    • Install Water Main tap
    • Complete parking lot and driveway
    • Start sidewalk grading
  • PROJECT FINANCE REPORT AS OF APRIL, 30TH 2018

 

APRIL CONSTRUCTION PICTURE