AUGUST REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into eighth month. During this reporting period activities were related to completion of 1st floor framing, 2nd floor concrete, electrical rough-in and start of 2nd floor framing. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (AUGUST. 2018)
    • Complete 1st Floor Interior Framing
    • Start working on Roof Installation
    • Start Electrical, Plumbing & HVAC Rough Ins
    • Complete 2nd Floor Concrete Pour

 

  • UPCOMING WORK (SEPTEMBER. 2018)
    • Continue work on 2nd Floor Interior Framing
    • Start Low Voltage cabling
    • Continue with Roof Installation
    • Continue with Electrical, Plumbing & HVAC
  • PROJECT FINANCE REPORT AS OF AUGUST, 31ST 2018

AUGUST CONSTRUCTION PICTURES