AUGUST REPORT
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into eighth month. During this reporting period activities were related to completion of 1st floor framing, 2nd floor concrete, electrical rough-in and start of 2nd floor framing. Here are updates for the past month, and activities planned for next month.
-
COMPLETED WORK (AUGUST. 2018)
- Complete 1st Floor Interior Framing
- Start working on Roof Installation
- Start Electrical, Plumbing & HVAC Rough Ins
- Complete 2nd Floor Concrete Pour
-
UPCOMING WORK (SEPTEMBER. 2018)
- Continue work on 2nd Floor Interior Framing
- Start Low Voltage cabling
- Continue with Roof Installation
- Continue with Electrical, Plumbing & HVAC
-
PROJECT FINANCE REPORT AS OF AUGUST, 31ST 2018