February Report

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) started on January 15th. Construction is expected to last 14 months. Here are updates for the past month, and activities planned for next month. Insha’Allah, a monthly update will be provided to the community.

 

  • COMPLETED WORK (FEB. 2018)
    • Piers Installation
    • Grade beam Installation
    • Started underground Plumbing work
    • Started underground electrical work
    • Building Steel fabrication

 

  • UPCOMING WORK (MARCH. 2018)
    • Piers Installation
    • Grade beam Installation
    • Started underground Plumbing work
    • Started underground electrical work
    • Building Steel fabrication

 

 

 

 

 

  • PROJECT FINANCE REPORT AS OF MARCH, 7TH 2018

February Construction Picture