January Report
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) started on January 15th. Construction is expected to last 14 months. Here are updates for the past month, and activities planned for next month. Insha’Allah, a monthly update will be provided to the community.
-
COMPLETED WORK (JAN. 2018)
- Mobilization
- Site preparation work (Clearing, Grubbing, Select fill and compaction)
- Clean Storm Drains & Inlets
- Fix Security Fence
- Rebar for Drill Piers
-
UPCOMING WORK (FEB. 2018)
- Drill piers installation and inspection
- Concrete Pour and Curing
- Plumbing work
- Set rebar for Slab
- Steel Structure Fabrication
- Slab pour
.
-
PROJECT FINANCE REPORT AS OF FEB, 5TH 2018