January Report

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) started on January 15th. Construction is expected to last 14 months. Here are updates for the past month, and activities planned for next month. Insha’Allah, a monthly update will be provided to the community.

 

  • COMPLETED WORK (JAN. 2018)
    • Mobilization
    • Site preparation work (Clearing, Grubbing, Select fill and compaction)
    • Clean Storm Drains & Inlets
    • Fix Security Fence
    • Rebar for Drill Piers

 

  • UPCOMING WORK (FEB. 2018)
    • Drill piers installation and inspection
    • Concrete Pour and Curing
    • Plumbing work
    • Set rebar for Slab
    • Steel Structure Fabrication
    • Slab pour

 

 

.

  • PROJECT FINANCE REPORT AS OF FEB, 5TH 2018

 

 