Thursday, 26 December 2024 / 24 Jumada II 1446


In the name of Allah, the Beneficent, the Merciful

  • Fajr 05:52AM
  • Sunrise 07:16AM
  • Zuhr 12:23PM
  • Asr 03:53PM
  • Maghrib 05:49PM
  • Isha 06:36PM


In the name of Allah, the Beneficent, the Merciful

Thursday, 26 December 2024 / 24 Jumada II 1446
  • Fajr 05:52AM
  • Sunrise 07:16AM
  • Zuhr 12:23PM
  • Asr 03:53PM
  • Maghrib 05:49PM
  • Isha 06:36PM

JULY REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into seventh month. During this reporting period activities were related to completion of building steel frame, deck installation and Interior Framing. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (JULY. 2018)
    • Complete Building Frame Installation
    • Complete deck installation
    • Install main water and waste water connections
    • Install Grease Trap
    • Complete 2nd Floor Concrete Pour
    • Start working on Interior Framing

 

  • UPCOMING WORK (AUGUST. 2018)
    • Continue work on Interior Framing
    • Start Electrical, Plumbing and HVAC Rough In
    • Start Roof Installation
  • PROJECT FINANCE REPORT AS OF JULY, 31ST 2018

JULY CONSTRUCTION PICTURES

X