JULY REPORT
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into seventh month. During this reporting period activities were related to completion of building steel frame, deck installation and Interior Framing. Here are updates for the past month, and activities planned for next month.
-
COMPLETED WORK (JULY. 2018)
- Complete Building Frame Installation
- Complete deck installation
- Install main water and waste water connections
- Install Grease Trap
- Complete 2nd Floor Concrete Pour
- Start working on Interior Framing
-
UPCOMING WORK (AUGUST. 2018)
- Continue work on Interior Framing
- Start Electrical, Plumbing and HVAC Rough In
- Start Roof Installation
-
PROJECT FINANCE REPORT AS OF JULY, 31ST 2018