MARCH REPORT
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) has moved into its third month. During this reporting period most of the activities were related to Building Foundation. Here are updates for the past month, and activities planned for next month.
-
COMPLETED WORK (MARCH. 2018)
- Completed underground Plumbing and electrical work
- Set rebar for Slab
- Slab Pour and curing
- Building Steel fabrication
-
UPCOMING WORK (APRIL. 2018)
- Continue Steel fabrication
- Start of Building frame installation
- Install Water Main tap
-
PROJECT FINANCE REPORT AS OF MARCH, 23RD 2018