MAY REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and has moved into its fifth month. During this reporting period most of the activities were related to building steel frame fabrication and installation. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (MAY. 2018)
    • Portion of Sidewalk concrete pour and curing
    • Parking lot concrete pour and curing
    • Building Steel fabrication
    • Building Frame Installation

 

  • UPCOMING WORK (JUNE. 2018)
    • Complete Building frame installation
    • Install Sewer Connection
    • Continue sidewalk grading
  • PROJECT FINANCE REPORT AS OF MAY, 31ST 2018