November’s Report
Completed Work (July 2018)
Complete Building Frame Installation
-
-
Complete deck installation
-
Install main water and waste water connections
-
Install Grease Trap
-
Complete 2nd Floor Concrete Pour
-
Start working on Interior Framing
-
-
Completed Work (July 2018)
Complete Building Frame Installation
-
-
Complete deck installation
-
Install main water and waste water connections
-
Install Grease Trap
-
Complete 2nd Floor Concrete Pour
-
Start working on Interior Framing
-
-