SEPTEMBER REPORT
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into ninth month. During this reporting period activities were related to completion of 2nd floor framing, electrical and plumbing rough-in and start of HVAC and Roof installation. Here are updates for the past month, and activities planned for next month.
-
COMPLETED WORK (SEPTEMBER. 2018)
- Complete work on exterior walls
- Complete 2nd Floor Interior Framing
- Start working on Roof Installation
- Start working on Stair cases installation
- Continue with Electrical, Plumbing & HVAC
- Complete 2nd Floor Concrete Pour
-
UPCOMING WORK (OCTOBER. 2018)
- Complete Roof Installation
- Continue with Electrical, Plumbing & HVAC
- Continue working on Dry Wall Installation
- Start Fire Sprinkler system installation
- Start low voltage cabling
-
PROJECT FINANCE REPORT AS OF SEPTEMBER, 30TH 2018