Saturday, 27 July 2024 / 21 Muharram 1446


In the name of Allah, the Beneficent, the Merciful

  • Fajr 05:10AM
  • Sunrise 06:39AM
  • Zuhr 01:29PM
  • Asr 06:16PM
  • Maghrib 08:36PM
  • Isha 09:26PM


In the name of Allah, the Beneficent, the Merciful

Saturday, 27 July 2024 / 21 Muharram 1446
  • Fajr 05:10AM
  • Sunrise 06:39AM
  • Zuhr 01:29PM
  • Asr 06:16PM
  • Maghrib 08:36PM
  • Isha 09:26PM

OCTOBER REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into tenth month. During this reporting period activities were related to completion of Roof, continued work on electrical and plumbing rough-in; start of Fire Sprinkler system line and start of HVAC installation. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (AUGUST. 2018)
    • Complete 2nd Floor Interior Framing
    • Complete Roof and stair cases Installation
    • Continue with Electrical, Plumbing & HVAC
    • Start working on Fire Sprinkler system line and Low Voltage cabling

 

  • UPCOMING WORK (NOVEMBER. 2018)
    • Complete with Electrical, Plumbing & HVAC
    • Continue working on Dry Wall Installation
    • Complete Fire Sprinkler System and Voltage Cabling
    • Complete Building water proofing
    • Start working on exterior brick work
  • PROJECT FINANCE REPORT AS OF OCTOBER, 31ST 2018

OCTOBER CONSTRUCTION PICTURES

X