Thursday, 09 July 2020 / 17 Dhuʻl-Qiʻdah 1441


In the name of Allah, the Beneficent, the Merciful

  • Fajr 04:56AM
  • Sunrise 06:29AM
  • Zuhr 01:27PM
  • Asr 05:03PM
  • Maghrib 08:45PM
  • Isha 09:37PM


In the name of Allah, the Beneficent, the Merciful

Thursday, 09 July 2020 / 17 Dhuʻl-Qiʻdah 1441
  • Fajr 04:56AM
  • Sunrise 06:29AM
  • Zuhr 01:27PM
  • Asr 05:03PM
  • Maghrib 08:45PM
  • Isha 09:37PM

OCTOBER REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into tenth month. During this reporting period activities were related to completion of Roof, continued work on electrical and plumbing rough-in; start of Fire Sprinkler system line and start of HVAC installation. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (AUGUST. 2018)
    • Complete 2nd Floor Interior Framing
    • Complete Roof and stair cases Installation
    • Continue with Electrical, Plumbing & HVAC
    • Start working on Fire Sprinkler system line and Low Voltage cabling

 

  • UPCOMING WORK (NOVEMBER. 2018)
    • Complete with Electrical, Plumbing & HVAC
    • Continue working on Dry Wall Installation
    • Complete Fire Sprinkler System and Voltage Cabling
    • Complete Building water proofing
    • Start working on exterior brick work
  • PROJECT FINANCE REPORT AS OF OCTOBER, 31ST 2018

OCTOBER CONSTRUCTION PICTURES

X