OCTOBER REPORT
-
SUMMARY
Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into tenth month. During this reporting period activities were related to completion of Roof, continued work on electrical and plumbing rough-in; start of Fire Sprinkler system line and start of HVAC installation. Here are updates for the past month, and activities planned for next month.
-
COMPLETED WORK (AUGUST. 2018)
- Complete 2nd Floor Interior Framing
- Complete Roof and stair cases Installation
- Continue with Electrical, Plumbing & HVAC
- Start working on Fire Sprinkler system line and Low Voltage cabling
-
UPCOMING WORK (NOVEMBER. 2018)
- Complete with Electrical, Plumbing & HVAC
- Continue working on Dry Wall Installation
- Complete Fire Sprinkler System and Voltage Cabling
- Complete Building water proofing
- Start working on exterior brick work
-
PROJECT FINANCE REPORT AS OF OCTOBER, 31ST 2018