SEPTEMBER REPORT

  • SUMMARY

    Alhamdulillah, construction for the new facility (phase 1 – Al Hadi School building) continues and is entering into ninth month. During this reporting period activities were related to completion of 2nd floor framing, electrical and plumbing rough-in and start of HVAC and Roof installation. Here are updates for the past month, and activities planned for next month.

 

  • COMPLETED WORK (SEPTEMBER. 2018)
    • Complete work on exterior walls
    • Complete 2nd Floor Interior Framing
    • Start working on Roof Installation
    • Start working on Stair cases installation
    • Continue with Electrical, Plumbing & HVAC
    • Complete 2nd Floor Concrete Pour

 

  • UPCOMING WORK (OCTOBER. 2018)
    • Complete Roof Installation
    • Continue with Electrical, Plumbing & HVAC
    • Continue working on Dry Wall Installation
    • Start Fire Sprinkler system installation
    • Start low voltage cabling
  • PROJECT FINANCE REPORT AS OF SEPTEMBER, 30TH 2018

SEPTEMBER CONSTRUCTION PICTURES